top of page
Search

Top EPC Contract Risks in Solar and Battery Storage Projects (and How to Manage Them)

  • tullyblalock
  • Mar 23
  • 4 min read

Updated: Mar 23

I’ve drafted, negotiated, and managed disputes involving dozens—if not hundreds—of solar and storage EPC agreements and subcontracts. Over the past decade, these agreements have grown significantly in length and complexity as parties have learned—often the hard way—where risk needs to be clearly allocated.


Below are some of the most critical and frequently negotiated EPC contract issues. Getting these right on the front end can prevent costly disputes later.


I. Commercial & Financial Risk Allocation


1. Payment Structure

Payment mechanics directly impact project cash flow and risk.


Common structures include:

  • Milestone-based payments

  • Schedule of values / progress payments


Clear invoicing requirements and timing are essential.


2. Change Orders

Change order disputes are one of the most common sources of conflict.


Key issues include:

  • Notice and documentation requirements

  • Pricing methodology

  • Interim dispute resolution procedures


A well-defined scope of work is the best tool to minimize change orders.


3. Liquidated Damages (LDs)

Delay LDs are among the most heavily negotiated provisions.


Key considerations include:

  • Whether LDs reasonably approximate anticipated damages

  • Caps on LDs and whether they are the exclusive remedy

  • Interaction with termination rights

These provisions directly impact project economics and leverage.


4. Remedies Structure

The agreement should clearly define how remedies operate and interact.


Key issues include:

  • Whether remedies (including LDs) are exclusive or cumulative

  • Interaction with termination rights

  • Availability of actual damages


Lack of clarity can significantly affect risk exposure in a dispute.


5. Liability Caps

Limitation of liability provisions define the parties’ overall risk exposure.


Negotiation points include:

  • Overall caps vs. tiered caps

  • Carve-outs (e.g., fraud, indemnity, environmental liabilities)

  • Alignment with insurance coverage


These provisions are central to risk allocation.


6. Security / Credit Support

Performance security helps ensure contractor performance and protect against downside risk.


Key issues include:

  • Type of security (bonds, letters of credit, parent guarantees)

  • Amount and duration

  • Reduction and release mechanics


These protections are often critical to project financing.


II. Scope, Procurement & Interface Risk


7. Scope of Work

A detailed and unambiguous scope of work is foundational.


Best practice includes:

  • Coordination among legal, engineering, and project teams

  • Identification of gaps and overlaps

  • Clear definition of interface points


Ambiguities here are a leading cause of disputes.


8. Supply Chain & Equipment Procurement

Procurement risk has become a central issue in EPC agreements.


Key issues include:

  • Responsibility for late delivery or nonconforming equipment

  • Substitution rights

  • Coordination with equipment supply agreements


These risks can significantly impact both cost and schedule.


9. Permit Responsibility

Permitting obligations should be clearly divided between the parties.


Common approaches include:

  • Owner responsibility for land use and major project approvals

  • Contractor responsibility for construction-related permits


Ambiguity often leads to delay and cost disputes.


10. Site Conditions

Unforeseen site conditions can materially impact cost and schedule.


Key issues include:

  • Responsibility for differing or unknown conditions

  • Reliance on owner-provided data

  • Entitlement to change orders


These issues frequently arise during construction.


11. Interconnection & Grid Risk

Interconnection is often a critical path item with significant uncertainty.


Key issues include:

  • Responsibility for interconnection facilities and upgrades

  • Coordination with utilities and system operators

  • Risk of delays and cost overruns


These risks can materially affect project viability.


III. Schedule & Completion Risk


12. Schedule & Excusable Delay

Schedule risk must be clearly allocated across multiple potential delay sources.


Typical categories include:

  • Owner-caused delays

  • Interconnection and permitting delays

  • Force majeure events


Clarity is essential to avoid disputes over delay responsibility.


13. Completion Definitions & Milestones

Project milestones should be clearly defined and aligned with project requirements.


Key issues include:

  • Definitions of mechanical, substantial, and final completion

  • Punchlist thresholds

  • Alignment with payment, LDs, and financing requirements


Disputes often arise around whether completion has been achieved.


14. Performance Testing

Performance testing provisions are highly technical and require careful review.


Key issues include:

  • Testing protocols and conditions

  • Error bands or tolerances

  • Retesting rights and remedies


These provisions determine whether performance obligations are met.


IV. Performance & Long-Term Risk


15. Warranties

Warranty structure significantly impacts long-term risk allocation.


Common issues include:

  • Warranty duration

  • Allocation of equipment defect risk

  • Responsibility for “in-and-out” costs


These provisions affect post-completion exposure.


16. Battery-Specific Issues


Battery storage projects introduce additional technical and commercial considerations.


Key issues include:

  • Degradation guarantees

  • Round-trip efficiency guarantees

  • Augmentation obligations

  • Availability vs. capacity guarantees

  • EMS / controls integration


These issues require careful coordination between technical and contractual terms.


V. Legal & Regulatory Risk


17. Change in Law

Regulatory change is an ongoing risk in energy projects.


Key issues include:

  • Allocation of compliance costs

  • Scope of covered changes

  • Interaction with tax credit requirements


Clear allocation helps avoid future disputes.


18. Tariff Risk

Tariff exposure can materially impact project cost.


Key issues include:

  • Responsibility for increased costs

  • Price adjustment mechanisms

  • Timing and procurement considerations


This has become an increasingly important issue.


19. Investment Tax Credit (ITC) Compliance

Tax credit requirements introduce significant contractual risk.


Key issues include:

  • Prevailing wage and apprenticeship compliance

  • Foreign Entity of Concern (FEOC) restrictions

  • Documentation and audit support


These requirements can directly affect project economics.


VI. Risk Transfer & Dispute Framework


20. Indemnification

Indemnity provisions allocate risk between the parties.


Key issues include:

  • Scope of covered claims

  • Treatment of environmental liabilities

  • Allocation of comparative fault


These provisions can have significant financial implications.


21. Insurance

Insurance requirements should align with contractual risk allocation.


Key issues include:

  • Builder’s risk coverage

  • Coverage limits and deductibles

  • Additional insured requirements


Coordination with insurance advisors is important.


22. Force Majeure

Force majeure provisions define relief for events outside the parties’ control.


Key issues include:

  • Scope of covered events

  • Exclusions

  • Impact on schedule and termination rights


These provisions are often heavily negotiated.


23. Termination

Termination provisions define the parties’ rights in distressed scenarios.


Key issues include:

  • Events of default and cure periods

  • Termination for convenience

  • Payment obligations upon termination


These provisions affect leverage and downside protection.


Closing Thought

EPC agreements are not just construction contracts—they are risk allocation frameworks that can determine whether a project succeeds or fails financially.


Careful drafting and negotiation on the front end is almost always less expensive than resolving disputes on the back end.


If you are negotiating or evaluating an EPC contract, I would be glad to discuss your project.



This article is provided for general informational purposes only and does not constitute legal advice. No attorney-client relationship is formed by reading this article. Readers should consult qualified legal counsel regarding any specific legal matter.



 
 
 

Recent Posts

See All

T. Blalock Law LLC

© 2025 

 

bottom of page